Check your Engine: Work In Progress Limit Matters

agile
kanban
productivity
software-development
Check your Engine: Work In Progress Limit Matters

In recent years, I have worked on projects where keeping developers busy was a primary rule. Understandably, developers are expensive. Keeping them busy is one way of getting the most value out of them, right?

This is not only a common management view; often developers themselves are eager to stay busy. For a freelancer, being busy is billable — spinning in your chair while waiting for a review doesn’t pay the bills. As a developer, it’s easy to keep yourself busy and signal this to others, including management. You are there to work, so you pull a new ticket and report your progress in the daily stand-up while your other ticket is waiting for a review or some other feedback. But is that really productive? Being busy is not inherently productive and can even be counterproductive, causing more harm than value.

Keep Pushing Down the Line

Convey belt with yellow packages, rough minimalistic sketch

A common pattern I’ve observed is the decoupling of ongoing developer work. The result is often an attempt to optimize the number of tickets in progress — not by decreasing the count, but by increasing it. This isn’t a willful act, but rather the result of a sloppy habit gaining the upper hand.

DE: Das Gegenteil von gut ist gut gemeint

EN: The opposite of good is good intentions

– German proverb

In an attempt to be productive and valuable, developers can harm the project by continually “pushing down the line.” Your implementation is done but requires approval. Why not stay busy in the meantime by starting the next work package? It has to be done anyway! What’s the alternative, spinning in your chair? Is there any problem with interleaving work to maximize throughput?

There are a lot of problems with this approach of unintentionally increasing the amount of work in progress. Most of them have been common sense for a long time, but to underline my conclusion, let’s examine a few.

The Problem of Decoupled Work

To be fair, there are projects where decoupling work is the only way forward, for example, in a multi-timezone or decentralized open-source project. But often enough, developers work more traditionally together in a company setting. Sure, fully remote teams are more common now, but it’s also easier than ever to collaborate with live interactions. In short: there is often no reason not to have direct and ongoing interactions between developers and business people.

  1. Business people and developers must work together daily throughout the project.

– Agile Manifesto

From a developer’s perspective, there shouldn’t be a “personal” ticket. Nothing a developer starts should be worked on exclusively. It’s harmful and unproductive to have five developers working on five different tickets simultaneously because it hinders direct interaction and raises communication overhead exponentially. In this scenario, when one developer needs help, they have to contact and onboard at least one other developer. This involves context switching, introduces delays, and often results in suboptimal support. Sometimes you have to call in a third developer, and so on.

It’s more effective to work together on one ticket. Studies indicate that pairing or ensemble programming leads to higher quality code 1,2.

  1. The most efficient and effective method of conveying information to and within a development team is face-to-face conversation.

– Agile Manifesto

If this is your normal modus operandi, you tend to have the ideal information flow within your team. Are you able to work efficiently on multiple topics at the same time? Probably not. Why should a development team, if parallelizing work is not advised and considered harmful? It should also be common sense that working together to find an excellent solution is better for the health of a project than working in isolation. A team should share the same goals, the same understanding of problems, and their solutions — so why shouldn’t they find those solutions in a shared effort, too?

Cost of Delay & Missing Early Feedback

  1. Our highest priority is to satisfy the customer through early and continuous delivery of valuable software.

– Agile Manifesto

Being agile is all about getting feedback as early as possible and acting on it. This enables continuous value delivery, which is not only a selling point for management but also raises the self-efficacy and well-being of the development team when they see they can deliver value quickly and with less friction.

  1. Deliver working software frequently, from a couple of weeks to a couple of months, with a preference for the shorter timescale.

– Agile Manifesto

We’ve come a long way; it’s now more common to have daily releases than releases every three years. The implementation may not always be perfect, but the common understanding is that shorter release cycles are better than longer ones.

Abandoning a ticket, even for half a day while waiting for a review, carries the same problems as a three-year release cycle, albeit on a different scale. The problem isn’t negligible just because things were worse in the past. We came this far because we know that early feedback is less costly than delayed feedback. The same is true when a change is deployed one day later than optimal. The entire developmemt feedback loop is about gaining feedback as early as possible: from linting your code and writing tests to pairing with colleagues, deploying to production, and actually seeing customers use your change. Observe and adapt. This isn’t just about a customer complaining about a bug (which they often don’t), but also about gaining feedback that your change, fully integrated, has not introduced unintended behavior.

When this feedback is delayed, the “observe and adapt” cycle is postponed to a phase where the change is less present in your mental context. You might run into the same category of problems as the infamous “big bang” releases, especially if your team resolves a congested board the next day. The problem is even bigger with an anti-pattern like late-integrating branches, because all changes are integrated as late as possible, not as soon as possible.

Sketch of the agile concept 'Observe and Adapt': 'Observe': a system of gears under a magnifying glass, 'Adapt': Drawing a new Gear

Advocating for a Hard Work In Progress Limit

Work In Progress (WIP) limits are fundamental constraints that cap the maximum number of tasks actively being worked on at any given time in software development processes. These limits serve as critical tools for optimizing team productivity, improving software quality, and ensuring sustainable workflow management in agile environments.

~ Perplexity

What is the solution™ to the problem of parallelized work? A Work In Progress (WIP) limit is not a silver bullet or even a solution in itself. It’s an indicator that the process has a defect. The line is congested, the pipe is clogged, your engine has a problem, and the check engine light is blinking. A WIP limit is a simple but effective metric that is easy to maintain and understand. Like other metrics, it doesn’t solve problems; it makes them transparent. A hard WIP limit is an artificial barrier on an otherwise unlimited resource (unless you are working with a physical board).

The WIP limit for your ongoing work is the check engine light for your process. It doesn’t point to a specific problem—it’s not an error code—it just indicates that something should be discussed and improved. Because it is so often ignored or not even considered, I see a WIP limit as more important than the unmotivated Retrospective rituals I have often attended.

DORA suggests keeping the WIP limit as small as possible — to a degree you actually have to work to achieve. It then automatically ceases to be just the next dogmatic ritual. It won’t work as the next metric you have to game, like story points for sprint velocity. If you don’t treat WIP as a dogmatic rule but understand the motivation behind it, you will start asking the correct and important questions. You will be forced to challenge the common “this is how we work.”

  • Do you really need a decoupled code review process?
  • Why don’t we deploy on Fridays? Are we collecting tickets for Monday?
  • Why do we spend so much time in planning when a ticket still gets stuck waiting for feedback from domain experts? Can we integrate them better into our process?
  • Should we deploy behind feature flags?
  • Are our increments too big?
  • Are we embracing active knowledge sharing, or are we misaligning our skills by decoupling our work?
  • Do we have a bottleneck in the team because only one person can solve a problem or review a change?
  • Where can I help to finish something?

The Rules Aren’t The Rules. They Are Questions in Disguise.

Despite all the recent fuss about agile and the decline of Scrum, a fundamental understanding of its principles and rituals is that they are meant to start discussions. Much of the Scrum framework is just a vehicle for focused conversation. The WIP limit does its part. Instead of keep pushing down the line, solve the congested conveyor belt.

For this, you need interaction within the team and probably with those outside of it. This brings actual value to your daily routine: instead of reporting progress, you start discussing how to solve actual problems. Starting the next ticket while your previous one waits is just avoiding an important chance to challenge your team’s productiveness. Conflict aversion doesn’t resolve the underlying reasons for problems. And unsolved problems tend to grow in importance, so it’s better to tackle them early than during an incident. If you feel comfortable deploying on Fridays because you are in a position to deploy anytime, then pushing out an emergency fix to solve a Friday incident becomes routine.

Because of Goodhart’s law, a metric shouldn’t be a goal. The WIP limit is hard to game, which makes it a valuable metric. A WIP limit becomes very annoying if it’s considered merely dogmatic. The more exceptions to the rule you allow, the less valuable the metric becomes, because you are just avoiding the discovery of the underlying problem. You can’t keep ringing an alarm without devaluing its purpose. So, it’s better to consider the WIP limit a hard limit the team is not allowed to raise or cross. Only by feeling the pain of a scarce resource do you learn to use it efficiently. Treat a hit limit as a blocker, so you actively coordinate and work on resolving the impediment.